Banner: SAFEGROUNDS Learning Network - a network managed by CIRIA

home > guidance > main SAFEGROUNDS guidance document

Good practice guidance for the management of contaminated land on nuclear and defence sites

 

Table of contents
1: Introduction
2: Key principles
3: Amplification of the key principles
4: Recommended approach
5: Identifying the preferred ption
6: Deciding on the option to be implemented
7: Implementing the chosen management options
8: Validating what has been done
9: References
10: Glossary
Appendix A. Further guidance for nuclear-licensed sites
Appendix B. Further guidance for defence sites

These HTML sections are extracts from the main document and appendices.

8: Validating what has been done

The purpose of validation is to check that the management option for the contaminated land has been implemented correctly, so that it will achieve the desired high level of protection of people and the environment (principle 1, Section 2). The steps involved are shown in Figure 5. The first two steps are the carrying out of monitoring and surveys (see Section 8.1) and the evaluation of the results of these (see Section 8.2). These results should be communicated to stakeholders, some of whom will be involved in deciding whether the option has been implemented correctly (principle 2). Records should be kept of all validation activities (principle 5 and see Section 8.3).

8.1 MONITORING AND SURVEYS

Monitoring is usually required after the option has been implemented as well as during it. There are specific requirements for monitoring at nuclear-licensed sites. At defence sites MoD has to be satisfied that work is completed in accordance with contractual conditions. Completion surveys and independent monitoring can be required by regulators, for example in order to discharge a planning condition, or surrender a Pollution Prevention and Control permit (which has replaced waste management licensing). In some circumstances there will be a need for third party independent monitoring under the conditions of a contract for the implementation of the option, or because it has been agreed with stakeholders that this will be done.

A description of typical of monitoring, planning and requirements is given in Harris et al. [1995], and approaches are recommended in EA [2000a]. Guidance in Baker et al. [2000] is also relevant. The post-implementation monitoring should make use of, and be consistent with, the approach used during implementation if possible. It is good practice to keep stakeholders informed throughout the process.

8.2 EVALUATION OF RESULTS

The results of validation monitoring and surveys will be evaluated by the site owner/operator, regulators and perhaps by other stakeholders. The outcome could be agreement that the option has been fully and correctly implemented, or a requirement for further implementation work. The Land Quality Assessment described in Part IIA guidance is a useful reference to determine that the state of the site meets the intended objectives.

8.3 RECORD KEEPING

It is particularly important to keep records of validation monitoring and surveys and of the evaluation of results. While each organisation involved (site owner/operator, regulators, independent monitoring organisations) will need to keep their own records, it is recommended that one organisation takes the responsibility for holding a complete set. It will usually be most appropriate for site owners/operators to do this and to include material about regulatory and independent validation in their own summary records (see Section 3.5.3).

Figure 5 Steps in Validation

Next

 

 

sitemap